Chimney Hollow 2024 Year In Review

With the final full year of scheduled construction at Chimney Hollow in the rearview, many project components are finished or nearing completion.

Poudre Valley REA Completes Underground Installation of Power to Valve House

Throughout the past two months, Poudre Valley REA completed the underground phase of work that brings power from County Road 18E to the on-site valve house.

Employee Spotlight: Don Montgomery

Stantec’s Senior Principal Engineer Don Montgomery has a pivotal role in the success of Chimney Hollow Reservoir.

Snow-covered view of the Chimney Hollow site.

Holiday Site Closure and Winter Construction Hours

The site will be shut down from Dec. 24-Jan. 2 for the holidays. Crews will continue to work throughout the winter 24 hours a day, six days a week.

Crews Complete Vital Connection Between Chimney Hollow, C-BT Infrastructure

The link is now complete between Chimney Hollow Reservoir and the existing water-distribution infrastructure that will carry supplies to the project’s participating communities.  

Valve House Nearly Enclosed and Final Two Valves to Arrive on Site in Spring

The process, which took a little over three months, included installing the prefabricated steel walls and roof panels around the entire 120-by-120-foot building.  

Chimney Hollow Project Nearing Operational Readiness

Northern Water’s Municipal Subdistrict staff and key project contractors are making great progress on getting the Chimney Hollow Reservoir Project ready for operations in 2025.

Employee Spotlight: Jordan Hall

As an Earthworks Project Manager for Barnard Construction, Jordan Hall oversees many of the key features of the Chimney Hollow construction project.

Last lift of clay is placed on the Chimney Hollow Saddle Dam in November 2024

Saddle Dam at Chimney Hollow Reservoir Nears Completion 

The $10 million Chimney Hollow saddle dam, 2.5 miles south of the main dam at the head of the valley, is slated for completion in December.