History
Firming Water Supplies from the Original Windy Gap Project
The Windy Gap Project was first proposed in 1967 by the cities of Boulder, Estes Park, Fort Collins, Greeley, Longmont and Loveland. Built between 1981 and 1985 and located on the West Slope near Granby, Windy Gap consists of a diversion dam on the Colorado River, a pump plant and a 6-mile pipeline to Lake Granby, the largest storage reservoir in the Colorado-Big Thompson Project system.
The Windy Gap Firming Project, of which Chimney Hollow Reservoir is a main component, will improve the reliability of, or firm, water supplies from the original Windy Gap Project, which started delivering water in 1985. It was understood the original Windy Gap Project would require additional storage to achieve firm water supplies. The Windy Gap Firming Project has been reviewed under the federal National Environmental Policy Act. This review started in 2003. NEPA and Colorado's requirement for a plan focused on fish and wildlife are among several processes in place to identify mitigation measures that will address the project's impacts.
-
20032003Project participants enter the federal permitting process and U.S. Bureau of Reclamation holds three formal "scoping" meetings.
-
20052005U.S. Bureau of Reclamation published two reports, one describing the purpose and need, and one identifying a range of alternatives that could meet the needs.
-
20082008U.S. Bureau of Reclamation publishes the Draft Environmental Impact Statement.
-
20092009Municipal Subdistrict offers West Slope benefits to facilitate project implementation.
-
20112011State officials approve the fish and wildlife mitigation plan and voluntary enhancement plan
-
2011U.S. Bureau of Reclamation publishes the Final Environmental Impact Statement.
-
20122012Grand County and the Municipal Subdistrict board approve agreements to create improvements to the Colorado River. Grand County issues 1041 permit.
-
20142014U.S. Bureau of Reclamation issues its Record of Decision and signs a carriage contract to transport water to Chimney Hollow Reservoir.
-
20162016Colorado issues a 401 Water Quality Certification.
-
20172017U.S. Army Corps of Engineers issues its final Record of Decision.
-
2019December 2019The Board of Directors of the Northern Water Municipal Subdistrict chooses a contractor to build Chimney Hollow Dam. Barnard Construction Inc. of Bozeman, Mont., will enter into a $485.4 million contract that calls for the construction of a 355-foot-tall asphalt-core dam in the valley west of Carter Lake in southern Larimer County.
-
2020Dec. 10, 2020Federal Court rules in favor of the Windy Gap Firming Project, clearing the way for construction of Chimney Hollow Reservoir near Berthoud.
-
2021April 21, 2021The Subdistrict reaches an agreement with several environmental groups settling the lawsuit and appeal. The $15 million settlement will benefit aquatic habitat on the West Slope. The settlement will allow construction of Chimney Hollow Reservoir beginning in August 2021.
-
Aug. 6, 2021The Northern Water Municipal Subdistrict breaks ground on Chimney Hollow Reservoir, culminating a 20-year permitting process. Chimney Hollow Reservoir is a key component for these Windy Gap Firming participants: Broomfield, Platte River Power Authority, Loveland, Greeley, Longmont, Erie, Little Thompson Water District, Superior, Louisville, Fort Lupton, Lafayette and Central Weld County Water District. Each of the reservoir project participants that provide residential water service has committed to reduce per capita water supply through water conservation.
-
Aug. 16, 2021Northern Water’s Municipal Subdistrict issued a Notice to Proceed to Barnard Construction Co. Inc. to begin construction of Chimney Hollow Reservoir. Environmental and mitigation efforts have also begun in the Upper Colorado River basin.
-
Oct. 1, 2021Crews conduct the first blast at the Chimney Hollow Reservoir construction site. Blasts occur regularly, often multiple times a week, for the duration of the project.
-
2022January 2022Foundation grouting begins on the main dam at Chimney Hollow Reservoir.
-
Feb. 9, 2022In what is described as a “milestone” day, crews install a bridge to connect two sections of a new Larimer County access road at the Chimney Hollow Reservoir construction site.
-
Feb. 10, 2022Initial placement of the Chimney Hollow main dam plinth begins.
-
April 4, 2022Tunneling of the Chimney Hollow Reservoir inlet/outlet infrastructure gets underway.
-
July 7, 2022Crews place the first of 61 valves on-site as part of the conduit that will bring water into the reservoir. This valve is located in the valve vault on Bald Mountain approximately 700 feet above the top of the main dam and will provide isolation between the inflows to Chimney Hollow and the Colorado-Big Thompson Project. The 72-inch diameter valve weighs 23,000 pounds.
-
Aug. 1, 2022First piece of pipeline for the conduit installed.
-
Aug. 23, 2022Dignitaries from across the region gather to celebrate the start of construction at the Colorado River Connectivity Channel located in Grand County. Led by U.S. Sen. Michael Bennet, leaders of public agencies and private non-governmental organizations extol the value of the project that will reconnect two segments of the Colorado River above and below Windy Gap Reservoir.
-
Sept. 15, 2022A shutdown of the Colorado-Big Thompson (C-BT) Project goes into effect as crews cut into the existing C-BT infrastructure at the Bald Mountain Tunnel. A 126-inch steel pipe with a 72-inch steel offtake (known as a wye) is tied-in so that future water deliveries can be made to Chimney Hollow Reservoir.
-
Oct. 15, 2022Crews place the first section of the asphalt core. The asphalt is placed in 10-inch lifts until it reaches the top of the dam (approximately 350 feet). Rockfill occurs concurrently to stabilize the asphalt core, covering the plinth.
-
November 2022Crews complete the main dam rock excavation after 15 months of work on this component.
-
2023March 10, 2023Crews place first spillway slab.
-
March 31, 2023First valve house floor slab placed. The slam is 6.5 feet thick with about 280 cubic yards of reinforced concrete per slab.
-
March 31, 2023Barnard Construction surpasses 1 million hours at the Chimney Hollow Reservoir construction site.
-
April 1, 2023Crews begin full production on site with double shifts. All project components have begun.
-
April 11, 2023The main dam reaches original grade (elevation 5,545 feet), 50 feet up from the plinth.
-
April 21, 2023Chimney Hollow conduit reaches halfway point.
-
April 27, 2023One million cubic yards of zone 4 embankment placed on the main dam.
-
May 2, 2023Crews place 100th lift of asphalt on the main dam.
-
June 26, 2023The main dam at Chimney Hollow Reservoir hits 100 feet.
-
Oct. 25, 2023First water flowed through the Colorado River Connectivity Channel. The new channel around Windy Gap Reservoir hydrologically and ecologically reconnected two segments of the Colorado River for the first time in approximately 40 years.
-
November 2023Quarry blasting hit peak production supplying the approximate 62,000 tons of material daily. This material is keeping crews busy dumping a 100 ton load every two minutes, 20 hours a day, six days a week for the next two years.
-
Nov. 8, 2023Grouting complete on saddle dam.
-
December 2023Crews placed the final section of the concrete plinth, tying the above-ground features of the dam to the grout curtain and rock foundation below. It is secured by thousands of anchors and provides a water-tight bond between the foundation and asphalt core.
-
2024March 13, 2024Crews hole through on tunnel, connecting the upstream and downstream portions.
-
March 23, 2024Main dam hits halfway mark of 175 feet.
-
March 29, 2024Crews begin summer working hours, which includes two 12-hour shifts, six days a week.
-
April 2024Spillway construction reaches halfway point.
-
June 7, 2024Saddle dam clay embankment begins.
-
June 30, 2024Crews placed the tie-in lift that connects two sections of the main dam, separated by a natural rise in the bedrock. The 9-inch lift was placed partially by hand and partially by the asphalt paver. It ran about 3,000 feet and took crews 11 hours to complete.
-
July 29, 2024Alexander Mountain wildfire ignites north of the site, crews evacuated.
-
July 30, 2024Stone Canyon wildfire ignites south of the site, crews remain evacuated.
-
August 2024Crews installed the 25-ton gantry crane inside the valve house that will allow access for future maintenance.
-
Aug. 5, 2024Crews back to work after wildfire evacuation orders lifted.
-
Sept. 2, 2024Main dam hits 250 feet. Only 100 feet left to go!
-
Sept. 25, 2024Last slab of concrete placed for the box culvert portion of the spillway.
-
Sept. 26, 2024Grouting program completed.
-
Nov. 19, 2024Final lift of clay placed on the saddle dam.