April 27, 2023
By The Numbers: 1,000,000 Cubic Yards of Zone 4 Embankment Placed
As of 8 a.m. on April 27, crews placed 1,000,000 cubic yards of zone 4 embankment on the main dam. Zone 4 embankment is the majority of the rockfill that is placed on the main dam and consists of rocks 2-feet in diameter or less. Only 10 million more cubic yards to go!