Valve House Takes Shape as Exterior Steel is Placed

As the valve house begins to take shape, crews are wrapping up all valve installations inside. At the end of July, crews set and installed the 25-ton gantry crane that will allow access to maintain valves in the future. There are a few more valves that will be installed with the gantry crane once they arrive on site. 

Walls and ramps were completed over the last couple weeks and crews plan to have the valve house fully enclosed by the end of September.  