Inlet/Outlet Works
The entire inlet/outlet works are nearing completion. In 2024, the Chimney Hollow Conduit was finished, the valve house was fully enclosed, the inlet/outlet tunnel was completed, and the inlet/outlet tower will be completed in early 2025. Crews continue to install conduit from the valve house through the tunnel and are working on electrical and fiber connections to remotely operate and monitor the project. As work areas are completed, crews are constructing the final grade for the project, including removing temporary construction roads. Disturbed areas are covered with topsoil and vegetated with native seed mix for a successful establishment next spring.
Spillway
All of the reinforced concrete for the spillway was completed in 2024, with the final backfill wrapping up in early 2025. Additionally, the Carter Lake interconnect is now complete and will allow Northern Water to send water to Carter Lake from Chimney Hollow or Pinewood reservoirs.
Quality Control
The quality control program performed almost 3,400 earthworks tests and about 2,000 concrete tests, maintaining quality measures required on site.
Despite some setbacks in 2024, including six adverse weather delays and four days lost to mandatory evacuations from nearby wildfires, the project is still a couple of weeks ahead of schedule. As construction wraps up in summer 2025, project managers plan to begin filling the reservoir, which is expected to take about three years. Larimer County will manage the reservoir’s recreation and is expected to begin construction of trails and parking lots after the reservoir construction is complete.